Opentecture

Buildings, engineered to come apart.

4 cm grid · Reversible joints · Open source

About

The problem

Every change to a stick-built house starts with demolition.

Moving a wall means cutting drywall, pulling studs and filling a dumpster. The materials leave as waste, and the next change starts the same way.

How it works

The grid is the contract

Every part, hole and joint lands on a 40 mm (1⅝ in) grid. Parts from different makers fit because the grid says so.

Joints over glue

Parts bolt, clip and gasket together, with hard stops. No adhesive and no cutting on site, so a wall comes apart without damage.

Parts keep their value

A panel taken out of one building is stock for the next. We count what a building is worth when it comes apart, not only what it costs to put up.

How it works

Where we are

Real today

  • An open part library on the grid, with 3D files you can download.
  • A model house assembled from those parts in the browser.
  • Build sheets for three homes, priced line by line with sources and dates.
  • A build sequence for each method, stick-built and Opentecture.
  • A design notebook with test rigs specified and costed.

Hypothesis

  • 31 days on site for a two-bedroom home, against 82 stick-built.
  • At volume, about $194,000 all-in against $198,000 stick-built, mostly from fewer days on site.
  • About $52,000 of parts recoverable at end of life, against about $1,000.
  • Gasketed seams that still seal after 50 cycles.

Next: Rig 1, a $340 hot-box test of cartridge insulation against a standard batt. Results land in the design notebook with dates, and each hypothesis keeps its label until a rig or a build proves it.

Get involved

We want builders, owners, engineers and makers who will check the numbers. Browse the parts, propose one, or tell us where the math is wrong.